Windows installed and WRB (almost) installed.

The framing at 125 Midway is complete and the building is essentially "dried-in" - all the windows are installed, the sliding glass doors are in place, the roof membrane is down, and, with few exceptions, the building paper is on. This is always a great moment in a project when you can walk through a fully framed building and finally "see" the spaces that have until now only existed on paper. So, what's the verdict? We're incredibly pleased with the results so far: the unit layouts are working very nicely, the proportions feel right, and some of the last minute changes have clearly paid off. There are a couple things that we've had to reconsider, but it wouldn't be a construction project without a couple of revisions.  