Project Update: 125 Midway

125 Midway is nearing completion - the punch list might even be starting to get shorter rather than longer. Jordan's crew is doing a great job with all the finish work and tying up all the loose ends. The parking lot and drive was completed, the landscaping installed, metal railings are being fabricated and installed, tilework, finish cabinetry, and accessories continue in the units. It's all shaping up very nicely. We're scheduled for final blower door tests next week and will be sure to share the results. Check out project photos below.